01 / Summary
What are the pros and cons of geothermal energy?
| Pros | Evidence | Cons | Evidence |
|---|---|---|---|
| Runs day and night in any weather | 65.9% US capacity factor, 2025 (EIA) | High up-front cost | drilling is 30% to 57% of a new plant's capital cost (NLR) |
| Very low emissions | about 99% less CO2 and 97% less sulfur compounds than fossil plants (EIA) | Exploration risk | baseline exploration drilling success rate 60% (NLR) |
| No fuel to buy | contracts at $67.50 to $99 per MWh fixed for 10 to 30 years (NLR) | Limited natural sites | most US plants sit in western states and Hawaii (EIA) |
| Plants last for decades | The Geysers has produced power since 1960 (EIA) | Reservoirs can cool | 11 of 18 long-running Nevada fields produce cooler fluid than in their first year (regulator record) |
| Huge resource with new technology | about 7,500 GW of enhanced geothermal potential in the US (DOE analysis via NLR) | Induced earthquakes | a magnitude 5.5 earthquake at Pohang, South Korea, in 2017 was triggered by stimulation (Ellsworth and others, 2019) |
02 / Advantages
What are the advantages of geothermal energy?
It produces power around the clock
Heat underground does not depend on sun or wind. In 2025 the US geothermal fleet ran at a 65.9% capacity factor, meaning it produced 65.9% of what its available capacity could have delivered running flat out all year. Utility solar ran at 24.0%, wind at 33.8% and nuclear at 91.1%, by the EIA's count. Lazard models new geothermal plants at 80% to 90%.
It emits very little
Geothermal plants burn nothing. The EIA puts their emissions at about 99% less carbon dioxide and about 97% less sulfur compounds than fossil fuel plants. Binary-cycle plants pass the hot water through a heat exchanger and send it back underground, so they produce no air emissions at all.
The fuel is free and the price is fixed
Once the wells are drilled the heat costs nothing, so geothermal power sells on long fixed contracts. Public US agreements signed between November 2019 and June 2025 priced at $67.50 to $99 per megawatt-hour for 10 to 30 years, as compiled by the National Laboratory of the Rockies (NLR, formerly NREL).
Plants run for decades
The first geothermal power plant ran in Italy in 1904, and The Geysers in California has produced electricity since 1960, according to the EIA. NLR's cost baseline assumes a 30-year life for plant and reservoir.
The resource is enormous once drilling gets cheaper
Natural hot-water systems are rare, but hot rock is everywhere at depth. The US Department of Energy's Enhanced Geothermal Shot analysis estimated about 7,500 GW of enhanced geothermal potential in the United States, against about 2,700 MW of geothermal capacity running in 2025. Our guide to enhanced geothermal systems explains how that rock is put to work.
03 / Disadvantages
What are the disadvantages of geothermal energy?
Most of the money is spent before the first megawatt-hour
Lazard's 2026 estimate for a new geothermal plant is $5,135 to $6,635 per kilowatt, against $1,250 to $1,850 for utility solar. Drilling accounts for 30% to 57% of the capital cost, by NLR's 2025 analysis. That makes the price of geothermal power sensitive to interest rates; our cost guide shows by how much.
Wells can come up dry
A geothermal field is proven only by drilling into it. NLR's 2025 baseline assumes 60% of exploration wells at a new hydrothermal site succeed, in line with a global average of 59% recorded in 2013. Each miss costs millions of dollars.
Natural sites are limited
A conventional plant needs heat, water and permeable rock in the same place. That combination sits mostly near tectonic plate edges, and most US plants are in western states and Hawaii, according to the EIA. Enhanced and closed-loop systems are built to work without the natural water and cracks.
Reservoirs cool during a plant's life
Cold water injected back into the rock cools it over time. Nevada publishes the temperature of every producing well each month. Across 18 fields with ten or more years of record, the flow-weighted produced temperature fell by more than 5 °F in 11, held within 5 °F in 3 and rose in 4. At Blue Mountain it fell from 368 °F in 2009 to 281 °F in 2025. Fervo's Project Red well pair went from 347 °F in 2024 to 316 °F in July 2026. Operators answer with new wells, which is a running cost. The field-by-field table is in our guide is geothermal energy renewable.
Stimulating rock can trigger earthquakes
Enhanced systems open fractures with water under pressure, and that can set off earthquakes. In November 2017 a magnitude 5.5 earthquake struck Pohang, South Korea, injuring 135 people; a government-appointed research committee concluded it was triggered by stimulation at an enhanced geothermal pilot. Fervo Energy's 2026 Department of Energy award in Idaho includes a high-temperature geophone array to monitor this.
Some plants release gases
Geothermal fluid carries hydrogen sulfide and small amounts of carbon dioxide. Plants use scrubbers to remove the hydrogen sulfide, and most inject the steam and water back into the ground, according to the EIA. Emissions, water use and induced earthquakes are measured side by side in our guide to the environmental impacts of geothermal energy.
04 / Compared
Geothermal against other power sources.
| Source | US capacity factor, 2025 | New-build cost, 2026, $/MWh unsubsidized | Runs at night |
|---|---|---|---|
| Geothermal | 65.9% | $67 to $111 | yes |
| Solar PV, utility | 24.0% | $40 to $98 | no |
| Wind, onshore | 33.8% | $37 to $99 | when the wind blows |
| Nuclear | 91.1% | $175 to $255 | yes |
| Gas, combined cycle | 58.7% | $51 to $129 | yes, with fuel |
Capacity factors from EIA Electric Power Monthly tables 6.07.A and 6.07.B; costs from Lazard's Levelized Cost of Energy+ version 19.0. Our firm clean power comparison sets geothermal against small reactors, fusion and space solar.
05 / Outlook
Which disadvantages new technology is working on.
- Drilling cost. Fervo Energy reported its Cape Station wells falling from $9.4 million to $4.8 million each, and NLR's 2025 cost curves cut 12% to 26% from the 2017 baseline. More in our guide to geothermal wells.
- Location. Enhanced geothermal reached commercial power at Cape Station, Utah, on 24 September 2026, by Fervo's account. Eavor's closed-loop plant at Geretsried, Germany, has sent power to the grid since December 2025.
- Power per well. Wells in superhot rock above 375 °C could deliver 30 to 50 MW each against about 10 today, according to ARPA-E. Their steel casing is the limit; that is our work, described in the superhot rock guide.
- Cooling. Wider, even flow through more fractures uses more rock and slows cooling. Our Project Red tracker scores a registered forecast of one well pair against the regulator record every month.
The companies doing this work are listed in our guide to geothermal companies.
06 / Questions
Common questions.
What is the biggest disadvantage of geothermal energy?
Up-front cost. Drilling makes up 30% to 57% of a new plant's capital cost, and the whole plant is paid for before it sells power. Lazard puts new geothermal at $5,135 to $6,635 per kilowatt, several times the cost of utility solar per kilowatt.
What is the main advantage of geothermal energy?
It delivers clean power day and night. US geothermal plants ran at a 65.9% capacity factor in 2025, against 24.0% for solar and 33.8% for wind, while emitting about 99% less carbon dioxide than fossil plants.
Is geothermal energy bad for the environment?
Its effects are small next to fossil fuels. Plants emit about 99% less carbon dioxide and 97% less sulfur compounds, scrub hydrogen sulfide and reinject their water. The local risks are induced earthquakes from stimulation and the land and water used at the site.
Why is geothermal energy not used more?
Conventional plants need rare spots where heat, water and permeable rock meet, and drilling is expensive and risky. Enhanced and closed-loop systems remove the need for natural water and cracks, and their drilling costs fell sharply between 2022 and 2025.
Can geothermal energy run out?
The Earth's heat will not run out, but a single reservoir can cool when heat is drawn faster than the rock refills it. In Nevada, 11 of 18 long-running fields produced cooler fluid in 2025 than in their first recorded year.
Does geothermal energy cause earthquakes?
Stimulating rock for enhanced systems can trigger earthquakes. A government-appointed committee linked the magnitude 5.5 Pohang earthquake of 2017 in South Korea to stimulation at an enhanced geothermal pilot. Fervo Energy's 2026 Department of Energy award in Idaho includes a high-temperature geophone array to monitor seismicity.
07 / Sources
Sources.
- US Energy Information Administration, Electric Power Monthly, capacity factors, table 6.07.A and table 6.07.B, release of 24 November 2026.
- EnergyTech, DOE selects Fervo, Zanskar and Quaise as part of $99M funding, 25 September 2026.
- US Energy Information Administration, Geothermal energy and the environment, Geothermal power plants and Where geothermal energy is found, read 27 November 2026.
- Lazard, Levelized Cost of Energy+, version 19.0, 13 July 2026.
- National Laboratory of the Rockies, Annual Technology Baseline 2025: geothermal, read 27 November 2026.
- Akindipe and Witter, 2025 Geothermal Drilling Cost Curves Update, NREL/CP-5700-92793, July 2025.
- Ellsworth and others, Triggering of the Pohang, Korea, earthquake (Mw 5.5) by enhanced geothermal system stimulation, Seismological Research Letters, 2019.
- Journal of Petroleum Technology, Hot prospects, 18 April 2024 (Cape Station well cost, company statement).
- Eavor Technologies, first electricity production at Geretsried, 4 December 2025. Company statement.
- ARPA-E, SUPERHOT program, read 20 November 2026.
- Nevada Division of Minerals, Geothermal Production and Well Data, workbook of 29 September 2026. Measured, operator-reported.
Text and tables on this page are licensed CC BY 4.0. Cite as: Toni Zemani, "Geothermal energy pros and cons, with the numbers behind each", Zemanium, 27 November 2026.